The work behind lifting Frederikshavn Church’s spire
As several hundred spectators watched around Frederikshavn Church, BMS lifted the large spire back onto the tower. For the team, the visible part of the job marked the culmination of preparations for a 32-tonne lift.
Watch the video at the bottom of the page, where Per explains the work, and follow the lifting of the spire. The interview is in Danish.
The spire was renovated at ground level
The 28-metre spire had stood beside the church since BMS lowered it on 8 June 2026. The old copper cladding was leaking, and the structure had suffered water damage. The renovation therefore took place at ground level before the spire was returned to its position in November.

Giving the team space to work
Before the lift, everyone involved held a final safety meeting. Only essential personnel remained on site during the operation, and radio communication was kept to what was necessary. One team member was raised in a personnel basket to rig the spire, while two others stood ready on the scaffolding to help position it.
“We lift the spire from its base,” explains Per Lillevang, a crane operator and supervisor from BMS Krangården Holstebro, in the on-site interview. He describes the connection to the base frame and the work carried out beforehand.
From the cab, Per monitored the weight, radius, height and wind, among other things. Cameras also gave him a view of parts of the crane. “We can see the winches back here, and we can see the counterweight,” he explains in the video.


The crane chosen for the job
Per operated the 650-tonne mobile crane. In this setup, the lifting capacity was 40 tonnes for a lifting weight of 32 tonnes, he explained from the crane.
The spire was lifted and positioned on the tower so that work on securing it could continue. After almost five months, Frederikshavn had its large church spire back.

Meet Per Lillevang, crane operator and supervisor from Holstebro